Waterproofing, building services and interior works

Follow the process of construction

2022.05.16.
Since our last December report, our construction work has progressed significantly:
 
N
The slabs above the 1st floor in all of our buildings have been cemented.
N
Utility relocations around the buildings, water and sewer constructions have been completed.
$
Waterproofing, building services, interior architecture and doors/windows installation works are in progress in the buildings.
Structural construction works will be completed by 15 June, according to plans.