Follow the process of construction
2022.05.16.
Since our last December report, our construction work has progressed significantly:
The slabs above the 1st floor in all of our buildings have been cemented.
Utility relocations around the buildings, water and sewer constructions have been completed.
Waterproofing, building services, interior architecture and doors/windows installation works are in progress in the buildings.
Structural construction works will be completed by 15 June, according to plans.